New bridge lowered into position as East London line extension work progresses
From Wikinews, the free news source you can write!
Saturday, March 29, 2008
Work to extend the East London railway line reached a significant milestone today as a new bridge was lowered into position over a street in Shoreditch, London. The line, previously part of the London Undeground, is being extended to become part of the London Overground network.
The 350 tonne, 35 metre long tied arch bridge required the use of Britain's largest mobile crane to get it into position.
Transport for London project manager Barrie Noble said, "I've been in this business a good many years and have led a fair few extraordinary projects, but lifting this bridge in really will be something to behold."
"I can't say how proud I am of the team behind it, both the TfL engineers and the contractors we are using."
The bridge was manufactured in Chepstow, Wales and assembled on-site.
A section of Shoreditch High Street will remain closed over the weekend as the bridge is secured in place. The East London line closed in December 2007 and is due to reopen in stages from 2010.
Gallery
Sources
- "Giant bridge fitted for rail line". BBC News, March 29, 2008
- "East London rail line moves forward with mobile crane". Builder & Engineer, March 29, 2008
- "Britain's biggest mobile crane helps build the new East London line". Transport for London, March 29, 2008
| This page is archived, and is no longer publicly editable.
Got a correction? Add the template {{editprotected}} to the talk page along with your corrections, and it will be brought to the attention of the administrators. Please note that due to our archival policy, we will not alter or update the content of articles that are archived, but will only accept requests to make grammatical and formatting corrections. Note that some listed sources or external links may no longer be available online due to age. |